Gibson road improvements remain on track for completion this calendar year. See the visual below for the "stages" of roadwork. Base lift paving of stages 1 and 2 has been completed. Base lift paving of stage 3 will be completed the week of Monday, October 24 and stage 4 the week of Monday, October 31. Final lift paving of the entire road will then follow and be completed the week of Monday, November 7. Gibson will then be painted and striped by December 1. This schedule is subject to change due to weather or other issues that may arise during construction.
WM pickups in the impacted areas will be conducted on Saturdays with a regular schedule resuming at the end of the work. If you have questions about your service, please call Waste Management Customer Service at (530) 662-8748.

The City thanks Woodlanders for their patience as we work to improve Gibson. To find out more about this and other projects, visit the City Projects page.