W. Woodland Safe Routes to School Project (W. Court St.)

CIP 17-09

Phase: Construction

Anticipated Completion:  December 2020 

Project Description

The West Woodland Safe Routes to School Project (W. Court Road Rehabilitation, CIP 17-09) began in 2018 to rehabilitate W. Court Street from West Street to CR98, resurface and restripe W. Woodland Avenue and California Streets and place “sharrows” (bike share the road legends) along primary bike corridors throughout town.

Work was complete on W. Woodland Ave., California St., and the bike corridors before work halted due to the discovery of shallow, privately owned utility lines that needed relocating before the roadway reconstruction could begin.

The remaining work, reconstruction of W. Court Street will begin the summer of 2020 with anticipated completion December 2020.