CIP 20-02
Phase: Construction
Anticipated Construction Start: July 2021
Anticipated Construction Completion: October 2021
Project Description
This project includes microsurfacing W. Cross (CR98 to West), W. Lincoln (CR98 to West), Cottonwood (W. Main to Gibson), Cottonwood (El Dorado to Gibson), and Clover (West to Walnut). The project also includes a grind and overlay of West Street from the southern City limits to Gibson Road.
Status Updates
The project is nearing completion and is currently on track to be finished by the end of October. The West Street grind and overlay is now complete along with 95% of all microsurfacing.
The striping portion will take place the week of October 4 and the remaining microsurfacing is scheduled for October 18.