CIP 19-05
Phase: Construction
Start Date: 2022
Anticipated Completion Date: Fall 2023
Project Description
The project will improve the mile-long corridor of Matmor Road from Main Street to Gibson Road, and the half-mile-long corridor of E. Gum Avenue from East Street to Matmor Road. The improvements include pavement rehabilitation, restriping narrower travel lanes to slow traffic, adding buffered bike lanes, constructing ADA-compliant curb ramps and sidewalk repairs, installing drainage improvements, and completing traffic signal improvements.
These improvements will transform the Matmor Road and E. Gum Avenue corridors into complete streets providing improved bicycle, pedestrian, and vehicle facilities to ensure the corridors meet the needs of all modes of travel.
Status Updates
Construction of this two-season project began in 2022.
Work during Summer and Fall 2022 consisted mainly of private utility relocations, concrete sidewalk and ADA ramp replacements, and traffic signal improvements.
We anticipate that the project will be largely complete by mid-September 2023.
Remaining work after this date will include:
- Minor road remediation (including traffic control as necessary)
- Reactivation of the E. Gibson & Matmor traffic signal (While adjacent to the Matmor & Gum project area, this work schedule is controlled by the Prudler Development Project at East Street & Sports Park Drive). This signal should be active before the end of October 2023.