CHAPTER 6. BUILDING CODES.*
Article III. Grading Regulations and Permitting Procedures.
Sec. 6-3-6. CEQA clearance and permits required.
Sec. 6-3-6-1 CEQA Clearance Required. Unless otherwise exempted by this
article, no person may perform any grading or be issued a grading permit without
first receiving CEQA clearance for the proposed project.
Sec. 6-3-6-2
Permits Required. Unless exempted by Section 3306.2 of the California Building
Code, no person shall do any grading without first obtaining a grading permit
from the city of Woodland. A separate permit is required for work on each site
unless the sites are contiguous, have the same ownership, and are included in
the CEQA clearance. (Ord. No. 1353, § 2 (part).)
<< previous | next >>